Or. Admin. Code § 330-230-0060

Current through Register Vol. 63, No. 10, October 1, 2024
Section 330-230-0060 - Failed Inspections or Reviews, Notice, Reconsideration
(1) The department may deny a tax credit or grant to, or may take action to recover any tax credit or grant already issued from, an applicant who has not resolved the problem identified in a failed project inspection or review.
(2) The department will provide written notice to the applicant explaining the reason for a denial, suspension or revocation of a tax credit certificate or grant due to a failed project inspection or review.
(3) The applicant may request reconsideration of the failed project inspection or review. A request for reconsideration must be received by the department within 30 calendar days of the date of the notice of failure.
(4) A request for reconsideration must include an explanation of why the applicant believes the project should pass inspection or review, a request for a new inspection or review and payment of the required re-inspection fee.
(5) The department may waive all or part of the re-inspection fee if it denies the request for reconsideration or accepts the applicant's explanation of special circumstances for the failure of the inspection or review.

Or. Admin. Code § 330-230-0060

DOE 12-2011(Temp), f. & cert. ef. 12-23-11 thru 6-19-12; DOE 7-2012, f. & cert. ef. 6-19-12

Stat. Auth.: OL 2011, Ch. 730, Sec. 34 - 51

Stats. Implemented: OL 2011, Ch. 730, Sec. 34 - 51