Leaks classified as grade one may be reclassified by performing a physical action to the pipeline (clamp, replacement, tape wrap, etc.) or pipeline facility. Venting, holes, aerators, or soil purging of a leak are not considered physical actions to the pipeline.
All below grade hazardous leaks repaired or reclassified, other than by the replacement of the affected section of pipe, must be reevaluated after allowing the soil to vent and stabilize but not more than thirty calendar days after such physical action.
Replaces: 4901:1-16-04
Ohio Admin. Code 4901:1-16-04
Five Year Review (FYR) Dates: 07/26/2026
Promulgated Under: 111.15
Statutory Authority: 4905.91
Rule Amplifies: 4905.91, 4905.93
Prior Effective Dates: 02/01/1991, 10/13/1994, 01/06/2005, 06/17/2006, 08/24/2007, 06/20/2008, 07/12/2010, 03/28/2014, 01/01/2015, 08/05/2021, 10/25/2021