Ohio Admin. Code 3745-52-264

Current through all regulations passed and filed through November 4, 2024
Section 3745-52-264 - Emergency coordinator - preparedness, prevention, and emergency procedures for large quantity generators

At all times, there shall be at least one employee either on the generator's premises or on call (i.e., available to respond to an emergency by reaching the facility within a short period of time) with the responsibility to coordinate all emergency response measures and implement the necessary emergency procedures outlined in rule 3745-52-265 of the Administrative Code. Although responsibilities may vary depending on factors such as type and variety of hazardous waste handled by the generator, as well as type and complexity of the facility, this emergency coordinator shall be thoroughly familiar with all aspects of the generator's contingency plan, all operations and activities at the facility, the location and characteristics of hazardous waste handled, the location of all records within the facility, and the facility's layout. In addition, this person shall have the authority to commit the resources needed to carry out the contingency plan.

Ohio Admin. Code 3745-52-264

Effective: 10/5/2020
Five Year Review (FYR) Dates: Exempt
Promulgated Under: 119.03
Statutory Authority: 3734.12
Rule Amplifies: 3734.12