Current through Supplement No. 395, January, 2025
Section 33.1-14-02-18 - Reports of welded repair or alterations1. All alterations and major repairs made to boilers in North Dakota must be reported on the appropriate national board form. The completed form must be sent to the chief boiler inspector by the repair concern effecting the repair or alteration within thirty days of the completion of the repair or alteration.2. Subject to the administrative procedures of the boiler inspection program and the approval of the inspector, repairs of a routine nature may be given prior approval and the requirement for the repair stamping may be waived. The National Board Inspection Code must be used as a guideline in determining repairs of a routine nature.N.D. Admin Code 33.1-14-02-18
Adopted by Administrative Rules Supplement 2020-377, July 2020, effective 7/1/2020.General Authority: NDCC 23.1-16
Law Implemented: NDCC 23.1-16