19A N.C. Admin. Code 5D.0205

Current through Register Vol. 39, No. 9, November 1, 2024
Section 05D .0205 - QUARTERLY PROGRESS REPORTS

All project contractors receiving grants from the Governor's Highway Safety Program must submit progress reports at 90-day intervals. Projects not submitting progress reports within 15 days following the end of a quarter are subject to having reimbursements withheld until compliance is satisfactorily achieved.

19A N.C. Admin. Code 05D .0205

Authority G.S. 136-18(5) and (12); 143B-357; 143B-360;
Eff. July 1, 1978;
Amended Eff. December 1, 1993; November 1, 1991; February 1, 1982;
Transferred and Recodified from 19A NCAC 03H .0200 Eff. January 1, 1999;
Pursuant to G.S. 150B-21.3A, rule is necessary without substantive public interest Eff. October 24, 2015.
Authority G.S. 136-18(5) and (12); 143B-357; 143B-360;
Eff. July 1, 1978;
Amended Eff. December 1, 1993; November 1, 1991; February 1, 1982;
Transferred and Recodified from 19A NCAC 03H .0200 Eff. January 1, 1999.