19A N.C. Admin. Code 2B.0511

Current through Register Vol. 39, No. 9, November 1, 2024
Section 02B .0511 - NOTICE REQUIRED BEFORE WORK BEGINS
(a) The applicant shall notify the Division Engineer or his appointed representative prior to beginning work on the highway right-of-way. Notice is not required for underground utility service connections and aerial crossings installed under blanket agreements.
(b) The Division Engineer or his representative shall notify the Bridge Maintenance Superintendent before work begins when attachments to structures are involved.

19A N.C. Admin. Code 02B .0511

Authority G.S. 136-18(5); 136-18(10); 136-93;
Eff. April 3, 1981;
Pursuant to G.S. 150B-21.3A, rule is necessary without substantive public interest Eff. September 6, 2016.
Authority G.S. 136-18(5); 136-18(10); 136-93;
Eff. April 3, 1981.