Current through Register Vol. 46, No. 50, December 11, 2024
Section 1001.12 - Exhibit 12: constructionExhibit 12 shall contain:
(a) A preliminary quality assurance and control plan, including staffing positions and qualifications necessary, demonstrating how applicant will monitor and assure conformance of facility installation with all applicable design, engineering and installation standards and criteria.(b) A statement from a responsible company official that:(1) that applicant and its contractors will conform to the requirements for protection of underground facilities contained in Public Service Law section 119-b, as implemented by Part 753 of this Title; and(2) the applicant will comply with pole numbering and marking requirements, as implemented by Part 217 of this Title.(c) Preliminary plans and descriptions indicating design, location and construction controls to avoid interference with existing utility transmission and distribution systems, indicating locations and typical separations of proposed facilities from existing electric, gas, and communications infrastructure and measures to minimize interferences where avoidances cannot be reasonably achieved.(d) Specification of commitments for addressing public complaints, and procedures for dispute resolution during facility construction and operation.N.Y. Comp. Codes R. & Regs. Tit. 16 § 1001.12