STATE OF NEW YORK
DEPARTMENT OF PUBLIC SERVICE
REPORT OF SPECIFICATIONS FOR PROPOSED CONSTRUCTION
LIQUID PETROLEUM PIPELINE FACILITIES
General Information
1. Corporation name ____________ Date ________
2. Pipeline route:
From ____________
To ____________
3. Length ____________
4. New construction or reconstruction ____________
5. Counties traversed ____________
6. Towns traversed ____________
7. Cities traversed ____________
8. Villages traversed ____________
9. Estimated starting date ____________
10. Estimated completion date ____________
11. Pipeline identification name or number ____________
Pipe Specifications
1. Nominal outside diameter, D (inches) ____________
2. Nominal wall thickness, t (inches) ____________
3. Type and/or grade of pipe ____________
4. Manufacturer of steel ____________
5. Manufacturer of pipe ____________
6. Longitudinal joint type ____________
7. Specified minimum yield strength, SMYS (psi) ____________
8. Nominal ultimate strength (psi) ____________
9. Fracture toughness (minimum Charpy Energy in ft. lbs. at 20° F for buried pipe, -20° F for exposed pipe) ____________
10. Mill test pressure (psi) ____________
11. Is pipe new or used ____________
12. If used pipe is employed, describe inspection and reconditioning procedures ____________
____________
13. Are the physical and chemical specifications of pipe to be verified by outside laboratories? If yes, by whom? ____________ ____________
Operating Pressure and Stress
1. Maximum operating pressure, P (psi) ____________
2. Calculated pipe stress (hoop stress) = PD/2t (psi) ____________
3. Ratio of pipe stress to SMYS (percent) ____________
Welding
1. Percentage of welds to be radiographed, by location ____________
____________
2. How will the corporation certify the radiographic technician ____________
____________
____________
Railroad, Road, and Water Crossings
1. Railroad and road crossings:
Attach a list giving the location of each and indicating whether each is cased or uncased (if uncased, provide reason), and if heavier wall carrier pipe is used.
2. Lake, river, stream, or creek crossings:
Attach a list giving the location of each and describing any special construction precautions to be followed.
3. Pipeline encroachments:
Attach a list of any encroachments to railroads or roads, by location, and describe any special construction precautions to be followed.
Valves (see 49 CFR 195.260)
1. Number and spacing of manual sectionalizing valves ____________
____________
2. Type, make, and location of any automatic valves to be used
____________
____________
Minimum Cover and Clearance (see 49 CFR 195.248, 250)
If the minimum prescribed cover and/or clearance cannot be maintained, indicate the location, nature of problem, cover and/or clearance to be maintained, and any special precautions to be observed. Corrosion Control (see 49 CFR 195.242)
1. Type of field coating:
For pipe (if not factory coated) ____________
For welds and fittings ____________
2. Type of coating test:
Before backfill ____________
After backfill ____________
3. Type of cathodic protection system
____________
Pressure and Leakage Tests (see section 258.6 of this Part)
1. Test pressure ____________
2. Test medium ____________
3. Test duration ____________
4. Length of test section(s) ____________
Right-of-Way
1. Has necessary right-of-way been obtained from each party having interest in the right-of-way? If not, what is the status?
2. Have formal approval and all necessary permits been obtained from governmental agencies? If not, what is the status?
Products Transported
Pipeline certified to transport the following liquid petroleum products:
1. ____________
2. ____________
3. ____________
4. ____________
5. ____________
______________
Signature of corporation officer
______________
Title
N.Y. Comp. Codes R. & Regs. Tit. 16 § 258.13