N.M. Admin. Code § 20.9.6.8

Current through Register Vol. 35, No. 23, December 10, 2024
Section 20.9.6.8 - GENERAL REQUIREMENTS FOR CLOSURE AND POST CLOSURE CARE
A. Closure and post-closure care plans are required of all solid waste facilities that operated on or after May 14, 1989. The owner or operator of a solid waste facility that has closed but not submitted a closure and post-closure care plan shall submit such a plan within 180 days of the effective date of these regulations. The submitted plan shall meet the requirements of 20.9.6 NMAC.
B. The owner or operator of the solid waste facility shall prepare a written closure and post-closure care plan that describes the steps necessary for closure and post-closure care of the solid waste facility and any anticipated future uses of the property following closure.
C. Closure and post-closure care plans are required in the application for a permit or permit modification. One initial copy of the plan and two copies of the completed plan shall be submitted to the department.
D. The owner or operator of the solid waste facility shall notify the secretary in writing of the intent to close at least 90 days before closure occurs and shall notify the secretary in writing within 14 days after becoming a locked facility.
E. Closure and post-closure care plans for new solid waste facilities and modifications to existing facilities shall be approved as part of the facility permit.
F. All closure and post-closure care plans shall be approved by the secretary and may be subject to conditions.
G. Closure and post-closure care plans for existing non-permitted landfills that seek to close rather than continue to operate, shall be submitted for approval by the secretary within one year after the effective date of this part. The closure and post-closure care plan shall meet the requirements of 20.9.6 NMAC. After determining that the plan is complete, the secretary shall provide public notice of the plan in a newspaper of general circulation in the county where the facility is located. A non-adjudicatory hearing will be held if significant public interest warrants it. Approved closure and post-closure plans for unpermitted category 2 and 3 landfills shall be enforceable as a permit or regulation for purposes of 20.9.2 - 20.9.10 NMAC and the Solid Waste Act. Any landfill that operates after the effective date of these regulations shall have a closure and post-closure care plan approved as part of the permit, or shall seek approval of a closure and post-closure care plan.
H. Responses to the secretary's requests for additional information concerning a proposed closure and post-closure care plan shall be made within 90 days of receipt of such a request. The secretary may extend the response time for good cause.
I. Post-closure inspection and maintenance shall not be required of the facility if the owner or operator demonstrates to the secretary that all solid waste has been removed, requirements of the closure plan have been met, and following the removal of such wastes, a demonstration is made that the soil and ground water have not been contaminated.
J. All landfills, regardless of category, except construction and demolition debris landfills, which close after October 9, 1991, shall comply with the final cover requirements contained in 20.9.6.9 NMAC in addition to other closure requirements in effect at the time of closure.
K. The length of the post-closure care period may be decreased by the secretary if the owner or operator demonstrates that the reduced period is sufficient to protect public health, welfare, and the environment, or it may be increased by the secretary if the secretary determines that a longer period is necessary to protect health, welfare, and the environment. The time period for application of the provisions for financial assurance as defined in 20.9.10 NMAC shall be coincident with the time period of the post-closure care period. Any reduction or extension of the post-closure care period as described in this section shall be accompanied by an identical reduction or extension of the financial assurance provisions.
L. The owner or operator shall submit a closure report to the department within 60 days after closure completion. The report shall include:
(1) a summary of closure activities: and
(2) a certification by a New Mexico registered professional engineer that the closure of the solid waste facility has been completed and all conditions of the approved closure plan have been satisfied.
M. The active life of the facility terminates, and post-closure care begins, upon written verification by the department that the facility has been closed in accordance with the closure plan approved by the secretary.
N. The owner or operator shall submit a post-closure report to the department within 60 days after the post-closure period expires. The report shall include:
(1) a summary of post-closure activities: and
(2) a certification by a New Mexico registered professional engineer that the post-closure requirements, and if applicable, any corrective action requirements have been completed and all conditions of the approved post-closure care plan have been satisfied.
O. The post-closure care period for the facility terminates upon written verification by the secretary that the requirements of the approved post-closure care plan have been satisfied. If the secretary does not issue a verification, the secretary shall notify the owner or operator in writing that the activities required under 20.9.6 NMAC and 20.9.9 NMAC have not been conducted satisfactorily, and specify the reasons for such determination.
P. The secretary may require the owner or operator to amend the post-closure care plan if the secretary believes that the present or future implementation of the plan may cause a threat to human health or the environment.

N.M. Admin. Code § 20.9.6.8

20.9.6.8 NMAC - Rp, 20 NMAC 9.1.V.501, 8/2/2007