N.J. Admin. Code § 5:23-8.13

Current through Register Vol. 56, No. 24, December 18, 2024
Section 5:23-8.13 - Pre-project procedures

Before an asbestos abatement project begins, the owner shall have evaluated whether or not the scope of work for a specific project will require that all surfaces in the work area are to be HEPA vacuumed and/or wet-wiped. This is in order to remove any dust which may contain asbestos and might, therefore interfere with the final inspection and final air clearance level needed to reoccupy the building. The surfaces to be cleaned shall include, but not be limited to, all horizontal and vertical surfaces and such inside spaces as room ventilators, storage lockers, and utility and storage closets. The cleaning shall be accomplished by trained employees of the building owner as delineated in this subchapter before the asbestos abatement project begins or it shall be made part of the scope of work of an asbestos abatement project to be completed by the licensed contractor.

N.J. Admin. Code § 5:23-8.13

New Rule, R.1989 d.342, effective 7/3/1989.
See: 20 New Jersey Register 1130(b), 21 New Jersey Register 1844(b).
Section 8.3 formerly was "Enforcement; licensing; special technical services".
Recodified from 5:23-8.3 by R.1993 d.198, effective 6/7/1993.
See: 24 New Jersey Register 1422(a), 25 New Jersey Register 2519(b).
Prior text at section, "Asbestos encapsulation and enclosure", recodified as 5:23-8.16.