Current through Register Vol. 56, No. 23, December 2, 2024
Section 16:47-4.5 - Access permit applications(a) The maximum time frames for the review of various types of applications are summarized below. They are for the Department only and do not include any applicant time or time for Federal Highway Administration reviews of work on interstate highways, interchanges, or ramps. The Department's check of the completeness of an application is included in these timeframes.DEPARTMENT TIME FOR APPLICATIONS ACCEPTED FOR REVIEW (IN DAYS)
| Form | Minor | Major | Major With |
| | n1 | | Planning |
| | | | Review |
Single Family Residential Driveway | MT-32 | 35 | NA | NA |
Residence and Business Driveway | MT-32 | 35 | NA | NA |
Minor | MT-32 | 35 | NA | NA |
Government Driveway | MT-32 | 35 | 90 | 90 |
Major Use | MT-32 | NA | 90 | 90 |
Street Intersection | MT-160 | 35 | 90 | 90 |
Concept Reviews | MT-32 | NA | 90 | 90 |
Street Improvement | MT-158 | 35 | NA | NA |
Lot Consolidation or Subdivision | MT-155 | NA | 50 | NA |
Temporary Access Permit | No form # | 35 | NA | NA |
| | | | |
Notes: (NA means Not Applicable) |
1. If a traffic signal is involved, the review may take 45 additional days. |
(b) The time for the Department review of an application may be extended with the written consent of the applicant.(c) When an applicant fails to respond to a Department request for information within 90 days of the request, the application shall be considered withdrawn.N.J. Admin. Code § 16:47-4.5