Nev. Admin. Code § 703.2211

Current through October 11, 2024
Section 703.2211 - Information required in application

An application by a public utility for adjustments in rates or charges must include:

1. An exhibit in the format of a tariff showing in full the rates, fares or rules desired to be put into effect or the general relief requested.
2. An exhibit in the format of a tariff showing in full the rates, fares or rules which will be superseded by the proposed changes.
3. A complete and accurate explanation of the circumstances and conditions relied upon as justification for the application.
4. A statement indicating whether the utility has included adjustments to be certified pursuant to subsection 3 of NRS 704.110, a statement of expected changes in circumstances in accordance with subsection 4 of NRS 704.110, or both.
5. An exhibit referencing any prior proceeding before the Commission which has been held and which is related to any of the proposals contained in the application.
6. A brief description of the application which will be used by the Secretary in drafting the public notice required in NAC 703.160. This description must include:
(a) The utility's reasons for the application or filing of a tariff;
(b) The estimated effect that approval of the application or tariff by the Commission will have on the applicant's annual revenues; and
(c) The estimated effect that approval of the application or tariff by the Commission will have on rates and charges paid by each class of the utility's customers.
7. A proposed notice of hearing which conforms to the requirements of paragraphs (b), (c) and (d) of subsection 2 of NRS 233B.121.

Nev. Admin. Code § 703.2211

Pub. Service Comm'n, Gen. Order 3 Rule 16 § 3, eff. 10-14-82-NAC A 3-19-87; A by Pub. Utilities Comm'n by R107-07, 12-4-2007; R036-09, 11-25-2009

NRS 703.025, 704.210