Current through November 8, 2024
Section 585.745 - Submission, approval of plan to construct, remodel plant1. If, after December 16, 1982, a plant for manufacturing cosmetics is constructed or extensively remodeled, or an existing structure is converted for such a use, an applicant must submit plans to the Commissioner for his or her approval before the work is begun.2. The plans must include:(a) The layout and arrangement of the plant;(b) The materials to be used in construction; and(c) The location, size and type of any fixed equipment and facilities.3. The Commissioner's approval of a plan does not constitute his or her final approval of the facility. An actual inspection of the completed facility must be made before a final approval will be given to the applicant. Until such inspection is made and final approval of the facility is granted, the Commissioner will not issue a license.Nev. Admin. Code § 585.745
Comm'r of Food & Drugs, Cosmetics § 11, eff. 12-16-82