Unless operations have been commenced or the operator is proceeding with due diligence, a permit to drill an individual geothermal well or a permit to drill geothermal wells in a project area expires 24 months after the date on which it was issued unless extended by the Administrator for good cause shown.
Nev. Admin. Code § 534A.220
NRS 513.063, 534A.090