Section 278.330 - Time for review of final map; notice of decision; delay in recording map1. The Division or local agency shall review and either approve or disapprove the final map and related plans or the plan for improvements submitted in accordance with subsection 2 of NAC 278.290 within 30 days after receipt of the map and related plans or the plan for improvements.2. The Division or local agency shall give written notice of its approval or disapproval to the developer. If the Division or local agency disapproves the map or related plans or the plan for improvements, its notice must include the reasons for its action.3. If the developer fails to record an approved final map within the time allowed by NRS NRS 278.360, the developer must resubmit a tentative map through the governing body to the Division or local agency for its review and approval.Nev. Admin. Code § 278.330