Current through September 17, 2024
Section 129-4-005 - Notification to permit applicants and public005.01 The Department will determine if a permit application is complete within 60 days after receipt of the application and so notify the applicant. If the Department determines that the application is incomplete and additional information is necessary to evaluate or take final action on the application, the Department may request such information in writing and set a reasonable deadline for a response. The Department may determine that an application is complete, but later determine that additional information is needed to evaluate or take final action on the application.005.02 The Department will provide opportunity to the public to submit comments or request a public hearing on every PSD permit application approved in accordance with Chapter 10. 129 Neb. Admin. Code, ch. 4, § 005
Amended effective 7/15/2018Amended effective 9/28/2022