Current through Register Vol. 21, November 2, 2024
Rule 17.20.1507 - ENERGY GENERATION AND CONVERSION FACILITIES, INTERCONNECTION AND TRANSMISSION AGREEMENTS(1) An application must include: (a) either a copy of any and all interconnection and transmission agreements involving the proposed facility, or the following information for each such agreement: (i) a brief description of the obligations of and the benefits to the facility under the agreement;(ii) a list of all parties to the agreement;(iii) the time period during which the agreement is in effect;(iv) a summary of the terms of the agreement; and(v) the financial agreements; and(b) a description of all current and planned negotiations with respect to interconnection of the facility and transmission of energy. The description must include a list of the parties to any negotiations and a general discussion of the history and current status of the negotiations.Mont. Admin. r. 17.20.1507
NEW, 2001 MAR p. 2410, Eff. 12/7/01.75-20-105, MCA; IMP, 75-20-211, MCA;