Section 20 CSR 4240-22.010 - Policy Objectives

PURPOSE: This rule states the public policy goal that this chapter is designed to achieve and identifies the objectives that the electric utility resource planning process must serve.

(1) The commission's policy goal in promulgating this chapter is to set minimum standards to govern the scope and objectives of the resource planning process that is required of electric utilities subject to its jurisdiction in order to ensure that the public interest is adequately served. Compliance with these rules shall not be construed to result in commission approval of the utility's resource plans, resource acquisition strategies, or investment decisions.
(2) The fundamental objective of the resource planning process at electric utilities shall be to provide the public with energy services that are safe, reliable, and efficient, at just and reasonable rates, in compliance with all legal mandates, and in a manner that serves the public interest and is consistent with state energy and environmental policies. The fundamental objective requires that the utility shall-
(A) Consider and analyze demand-side resources, renewable energy, and supply-side resources on an equivalent basis, subject to compliance with all legal mandates that may affect the selection of utility electric energy resources, in the resource planning process;
(B) Use minimization of the present worth of long-run utility costs as the primary selection criterion in choosing the preferred resource plan, subject to the constraints in subsection (2)(C); and
(C) Explicitly identify and, where possible, quantitatively analyze any other considerations which are critical to meeting the fundamental objective of the resource planning process, but which may constrain or limit the minimization of the present worth of expected utility costs. The utility shall describe and document the process and rationale used by decision-makers to assess the tradeoffs and determine the appropriate balance between minimization of expected utility costs and these other considerations in selecting the preferred resource plan and developing the resource acquisition strategy. These considerations shall include, but are not necessarily limited to, mitigation of:
1. Risks associated with critical uncertain factors that will affect the actual costs associated with alternative resource plans;
2. Risks associated with new or more stringent legal mandates that may be imposed at some point within the planning horizon; and
3. Rate increases associated with alternative resource plans.