Mo. Code Regs. tit. 20 § 4240-20.045

Current through Register Vol. 49, No. 21, November 1, 2024.
Section 20 CSR 4240-20.045 - Electric Utility Applications for Certificates of Convenience and Necessity

PURPOSE: This proposed rule outlines the requirements for applications to the commission, pursuant to section 393.170.1 and 393.170.2, RSMo, requesting that the commission grant a certificate of convenience and necessity to an electric utility for a service area or to operate or construct an electric generating plant, an electric transmission line, or a gas transmission line that facilitates the operation of an electric generating plant.

(1) Definitions. As used in this rule, the following terms mean:
(A) Asset means:
1. An electric generating plant, or a gas transmission line that facilitates the operation of an electric generating plant, that is expected to serve Missouri customers and be included in the rate base used to set their retail rates regardless of whether the item(s) to be constructed or operated is located inside or outside the electric utility's certificated service area or inside or outside Missouri; or
2. Transmission and distribution plant located outside the electric utility's service territory, but within Missouri;
(B) Construction means:
1. Construction of new asset(s); or
2. The improvement, retrofit, or rebuild of an asset that will result in a ten percent (10%) increase in rate base as established in the electric utility's most recent rate case;
(C) Construction does not include:
1. The construction of an energy generation unit that has a capacity of one (1) megawatt or less; or
2. The construction of utility-owned solar facilities as required under section 393.1665, RSMo;
3. Periodic, routine, or preventative maintenance; or
4. Replacement of equipment or devices with the same or substantially similar items due to failure or near term projected failure as long as the replacements are intended to restore the asset to an operational state at or near a recently rated capacity level.
(2) Certificate of convenience and necessity.
(A) An electric utility must obtain a certificate of convenience and necessity prior to-
1. Providing electric service to retail customers in a service area pursuant to section 393.170.2, RSMo;
2. Construction of an asset pursuant to section 393.170.1, RSMo; or
3. Operation of an asset pursuant to section 393.170.2, RSMo.
(B) The commission may, by its order, impose upon the issuance of a certificate of convenience and necessity such condition or conditions as it may deem reasonable and necessary.
(C) In determining whether to grant a certificate of convenience and necessity, the commission may, by its order, make a determination on the prudence of the decision to operate or construct an asset subject to the commission's subsequent review of costs and applicable timelines.
(D) An electric utility must exercise the authority granted within two (2) years from the grant thereof.
(3) In addition to the general requirements of 4 CSR 240-2.060(1), the following additional general requirements apply to all applications for a certificate of convenience and necessity, pursuant to sections 393.170.1 and .2, RSMo:
(A) The application shall include facts showing that granting the application is necessary or convenient for the public service;
(B) If an asset to be operated or constructed is outside Missouri, the application shall include plans for allocating costs, other than regional transmission organization/independent system operator cost sharing, to the applicable jurisdiction; and
(C) If any of the items required under this rule are unavailable at the time the application is filed, the unavailable items may be filed prior to the granting of authority by the commission, or the commission may grant the certificate subject to the condition that the unavailable items be filed before authority under the certificate is exercised.
(4) If the application is for authorization to provide electric service to retail customers in a service area for the electric utility under section 393.170.2, RSMo, the application shall also include:
(A) A list of those entities providing regulated or nonregulated retail electric service in all or any part of the service area proposed, including a map that identifies where each entity is providing retail electric service within the area proposed;
(B) If there are ten (10) or more residents or landowners, the name and address of no fewer than ten (10) persons residing in the proposed service area or of no fewer than ten (10) landowners, in the event there are no residences in the area, or, if there are fewer than ten (10) residents or landowners, the name and address of all residents and landowners;
(C) The legal description of the service area to be certificated;
(D) A plat of the proposed service area drawn to a scale of one-half inch (1/2") to the mile on maps comparable to county highway maps issued by the state's Department of Transportation or a plat drawn to a scale of two thousand feet (2,000') to the inch; and
(E) A feasibility study containing plans and specifications for the utility system, plans for financing, proposed rates and charges, and an estimate of the number of customers, revenues, and expenses during the first three (3) years of operations.
(5) If the application is for authorization to operate assets under section 393.170.2, RSMo, the application shall also include:
(A) A description of the asset(s) to be operated;
(B) The value of the asset(s) to be operated;
(C) The purchase price and plans for financing the operation; and
(D) Plans and specifications for the asset, including as-built drawings.
(6) If the application is for authorization to construct an asset under section 393.170.1, RSMo, the application shall also include:
(A) A description of the proposed route or site of construction;
(B) A list of all electric, gas, and telephone conduit, wires, cables, and lines of regulated and nonregulated utilities, railroad tracks, and each underground facility, as defined in section 319.015, RSMo, which the proposed construction will cross;
(C) A description of the plans, specifications, and estimated costs for the complete scope of the construction project that also clearly identifies what will be the operational features of the asset once it is fully operational and used for service;
(D) The projected beginning of construction date and the anticipated fully operational and used for service date of the asset;
(E) A description of any common plant to be included in the construction project;
(F) Plans for financing the construction of the asset;
(G) A description of how the proposed asset relates to the electric utility's adopted preferred plan under 4 CSR 240-22;
(H) An overview of the electric utility's plan for this project regarding competitive bidding, although competitive bidding is not required, for the design, engineering, procurement, construction management, and construction of the asset;
(I) An overview of plans for operating and maintaining an asset;
(J) An overview of plans for restoration of safe and adequate service after significant, unplanned/forced outages of an asset; and
(K) An affidavit or other verified certification of compliance with the following notice requirements to landowners directly affected by electric transmission line routes or transmission substation locations proposed by the application. The proof of compliance shall include a list of all directly affected landowners to whom notice was sent.
1. Applicant shall provide notice of its application to the owners of land, or their designee, as stated in the records of the county assessor's office, on a date not more than sixty (60) days prior to the date the notice is sent, who would be directly affected by the requested certificate, including the preferred route or location, as applicable, and any known alternative route or location of the proposed facilities. For purposes of this notice, land is directly affected if a permanent easement or other permanent property interest would be obtained over all or any portion of the land or if the land contains a habitable structure that would be within three hundred (300) feet of the centerline of an electric transmission line.
2. Any letter sent by applicant as notice of the application shall be on its representative's letterhead or on the letterhead of the utility, and it shall clearly set forth-
A. The identity, address, and telephone number of the utility representative;
B. The identity of the utility attempting to acquire the certificate;
C. The general purpose of the proposed project;
D. The type of facility to be constructed; and
E. The contact information of the Public Service Commission and Office of the Public Counsel.
3. If twenty-five (25) or more persons in a county would be entitled to receive notice of the application, applicant shall hold at least one (1) public meeting in that county. The meeting shall be held in a building open to the public and sufficient in size to accommodate the number of persons in the county entitled to receive notice of the application. Additionally-
A. All persons entitled to notice of the application shall be afforded a reasonable amount of time to pose questions or to state their concerns;
B. To the extent reasonably practicable, the public meeting shall be held at a time that allows affected landowners an opportunity to attend; and
C. Notice of the public meeting shall be sent to any persons entitled to receive notice of the application.
4. If applicant, after filing proof of compliance, becomes aware of a person entitled to receive notice of the application to whom applicant did not send such notice, applicant shall, within twenty (20) days, provide notice to that person by certified mail, return receipt requested, containing all the required information. Applicant shall also file a supplemental proof of compliance regarding the additional notice.
(7) Provisions of this rule do not create any new requirements for or affect assets, improvements, rebuilds, or retrofits already in rate base as of the effective date of this rule. Provisions of this rule may be waived by the commission for good cause shown.

20 CSR 4240-20.045

AUTHORITY: section 386.250, RSMo 2016.* This rule originally filed as 4 CSR 240-20.045. Original rule filed April 5, 2018, effective Nov. 30, 2018. Moved to 20 CSR 4240-20.045, effective Aug. 28, 2019.

*Original authority: 386.250, RSMo 1939, amended 1963, 1967, 1977, 1980, 1987, 1988, 1991, 1993, 1995, 1996.