Current through October 31, 2024
Rule 6-3-5.39 - Technical Project CapabilitiesA. Provide a sample Savings Measurement and Verification Plan from a completed GESP or SSC by the ESP including an estimate of the total number of measurement points currently being monitored by ESP for that project. B. Provide a sample Investment Grade Energy Audit conducted by the ESP which includes detailed energy and economic calculations for ESPs wanting to implement GESPCs or SSCs. C. Provide a sample Operations and Maintenance Manual developed by the ESP for a completed GESPC or SSC. D. Provide a sample Commissioning Plan from a GESPC or SSC implemented by the ESP. E. Provide a sample Final Design Specification for an installed ECM (e.g. HVAC, controls, etc.). F. Provide a sample Customer Savings Report from a GESPC or SSC implemented by the ESP. G. Provide a sample Customer Training Plan used in a GESPC or SSC implemented by the ESP. Miss. Code Ann. § 31-7-14 (Supp. 2017).