Current through December 10, 2024
The DGF Interconnection Agreement shall not become final until:
1. The milestones agreed to in the DGF Interconnection Agreement are satisfied;2. The DGF is approved by electric code officials with jurisdiction over the interconnection;3. The Interconnection Customer provides a Certificate of Completion to the EU. Completion of local inspections may be designated on inspection forms used by local inspecting authorities; and4. The Witness Test was successfully completed per the terms and conditions found in the Agreement.39 Miss. Code. R. 4-I-6-109