39 Miss. Code. R. 4-I-6-109

Current through December 10, 2024
Section 39-4-I-6-109

The DGF Interconnection Agreement shall not become final until:

1. The milestones agreed to in the DGF Interconnection Agreement are satisfied;
2. The DGF is approved by electric code officials with jurisdiction over the interconnection;
3. The Interconnection Customer provides a Certificate of Completion to the EU. Completion of local inspections may be designated on inspection forms used by local inspecting authorities; and
4. The Witness Test was successfully completed per the terms and conditions found in the Agreement.

39 Miss. Code. R. 4-I-6-109

Adopted 1/3/2016
Amended 8/12/2022
Amended 11/6/2022