39 Miss. Code. R. 4-I-4-102

Current through December 10, 2024
Section 39-4-I-4-102

When an Interconnection Request is for a DGF that includes multiple energy production devices at a site for which the Interconnection Customer seeks a single PCC, the Interconnection Request shall be evaluated on the basis of the aggregate Nameplate Capacity of the multiple devices.

39 Miss. Code. R. 4-I-4-102

Adopted 1/3/2016
Amended 8/12/2022
Amended 11/6/2022