Section 39-4-I-4-100

The EU shall review Interconnection Requests using one of the three levels of review procedures established below. The EU shall first use the level of DGF Agreement specified by the Interconnection Customer in the Application. The EU may not impose additional requirements not specifically authorized unless the EU and the Interconnection Customer mutually agree to do so in writing.