39 Miss. Code. R. 1-29- 103

Current through December 10, 2024
Section 39-1-29- 103 - Required Reports

For electric utilities, the required reporting under this Rule shall be comprised of three separate components: (1) the Integrated Resource Plan; (2) the Mid-point Supply-side Update; and (3) the Annual Energy Delivery Plan. Gas utilities are only required to file the Annual Energy Delivery Plan.

39 Miss. Code. R. 1-29- 103

Amended 10/8/2018
Amended 12/26/2019