Section 12-3-2.1-1-01650-1.02 - STARTING SYSTEMS
A. Coordinate Schedule for start-up of various equipment and systems.
B. Notify Professional and Owner seven (7) days prior to start-up of each system.
C. Verify each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, or other conditions which may cause damage.
D. Verify that tests, meter readings and specified electrical characteristics agree with those required by the equipment or system manufacturer.
E. Verify wiring and support components for equipment are complete and tested.
F. Execute start-up under supervision of responsible Contractors' personnel in accordance with manufacturers' instructions.
G. When specified in individual specification Sections, require Manufacturer to provide authorized representative to be present at site to inspect, check and approve equipment or system installation prior to start-up, and to supervise placing equipment or system in operation.
H. Submit a written report that equipment or system has been properly installed and is functioning correctly.