Current through December 10, 2024
Section 12-3-2.1-1-01311-1.09 - DISTRIBUTIONA. Distribution of Copies: Following joint review, distribute copies of updated schedules to Contractor's Project site, to Subcontractors, Suppliers, Professional and Owner.B. Reporting Problems: Instruct recipients to promptly report, in writing, problems anticipated by projections shown in schedules.12 Miss. Code. R. 3-2.1-1-01311-1.09