Minn. R. agency 183, ch. 8410, WATERSHED MANAGEMENT ORGANIZATION PLANS, pt. 8410.0050

Current through Register Vol. 49, No. 27, December 30, 2024
Part 8410.0050 - EXECUTIVE SUMMARY

Each plan shall have a section entitled "Executive Summary." The summary must include:

A. the purpose of the watershed management organization;
B. a map of the organization;
C. the primary issues addressed in the plan;
D. the main goals in the plan;
E. the major actions in the plan; and
F. the responsibilities of local governments related to implementation of the plan including any changes in responsibilities from the previous plan.

Minn. R. agency 183, ch. 8410, WATERSHED MANAGEMENT ORGANIZATION PLANS, pt. 8410.0050

17 SR 146
40 SR 6

Statutory Authority: MS s 103B.101; 103B.211; 103B.231; 103B.227