The owner or operator shall have a detailed written estimate, in current dollars, of the cost of closing the facility in accordance with parts 7045.0486 and 7045.0488 and applicable closure requirements in parts 7045.0526, subpart 9; 7045.0532, subpart 7; 7045.0534, subpart 7; 7045.0536, subpart 8; 7045.0538, subpart 7; 7045.0539, subparts 2 to 4; and 7045.0542, subpart 8; and Code of Federal Regulations, title 40, section 264.1102, as incorporated in part 7045.0550. The closure cost estimate must equal the cost of final closure at the point in the facility's active life when the extent and manner of its operation would make closure the most expensive, as indicated by its closure plan. The closure cost shall be estimated as follows:
During the active life of the facility, the owner or operator shall adjust the closure cost estimate for inflation within 60 days before each anniversary of the date on which the financial instruments used to comply with part 7045.0504 were established. Owners and operators using the financial test or corporate guarantee must adjust the closure cost estimate for inflation within 30 days after the close of the firm's fiscal year and before submission of updated information to the commissioner as specified in part 7045.0504, subpart 7, item E. The adjustment must be made as specified in items A and B using an inflation factor derived from the annual Implicit Price Deflator for Gross National Product as found in the Survey of Current Business issued by the United States Department of Commerce. The inflation factor is the result of dividing the latest published annual deflator by the deflator for the previous year. Adjustments must be made as follows:
During the active life of the facility, the owner or operator shall revise the closure cost estimate within 30 days after the commissioner approves the request to modify the closure plan, if the change in the closure plan increases the cost of closure. The revised closure cost estimate must be adjusted for inflation as specified in subpart 2.
The owner or operator shall supply the following to the commissioner upon request, including request by mail until final closure is completed: the latest closure cost estimate prepared in accordance with subparts 2 and 3 and, when this estimate has been adjusted in accordance with subpart 2, the latest adjusted closure cost estimate.
Minn. R. agency 167, ch. 7045, FACILITY STANDARDS, pt. 7045.0502
Statutory Authority: MS s 116.07