An owner or operator shall sample the soil following the spreading and incorporation of a batch of petroleum contaminated soil in accordance with the practices of subparts 2 to 4. The monitoring information that must be submitted to the commissioner is given in subpart 5.
Soil samples must be composite samples collected within a plot from the surface to a depth of eight inches using the procedures described in part 7037.3400. The minimum number of composite samples collected from the upper eight inches is based on the volume of the batch of petroleum contaminated soil actually spread and must follow the table in part 7037.2900, subpart 1, item A.
Monitoring of a plot in the year of spreading must be done at the times specified in the following table, until all soil analytical results in a single sampling round are ten parts per million total petroleum hydrocarbons or less.
Soil Spreading Date | Soil Sampling in First Calendar Year |
Before July 1 | Once in August and once in October |
July 1 to September 15 | Once in October |
After September 15 | None |
Monitoring in subsequent years must continue for those plots in which all soil analytical results are not ten parts per million total petroleum hydrocarbons or less. These sampling events must be done in June, August, and October.
Soil samples must be analyzed for total petroleum hydrocarbons, according to the methods under part 7037.3100, subpart 2, item C or D. The owner or operator shall analyze for additional compounds if requested by the commissioner. The commissioner shall request analysis for additional compounds if the commissioner determines that additional analysis is necessary to protect the public health and environment.
Within 30 days of receipt of laboratory results for the soil samples, the owner or operator shall submit the information specified in items A to F to the commissioner on a form prescribed by the commissioner:
An applicant shall furnish a copy of the information required in subpart 5 to the appropriate local government officials listed under part 7037.1200, subpart 3, at the same time or prior to submittal of the information to the commissioner.
Minn. R. agency 167, ch. 7037, pt. 7037.2700
Statutory Authority: MS s 116.07