The owner or operator of a solid waste management facility must cease to accept waste and must immediately close the facility in compliance with this part and parts 7035.2635 and 7035.2815 to 7035.2915, when:
The owner or operator must close the solid waste management facility in a manner that eliminates, minimizes, or controls the escape of pollutants to ground water or surface waters, to soils, or to the atmosphere during the postclosure period.
The owner or operator of a solid waste management facility shall submit a closure plan with the permit application, or as required by a closure document, or in order to establish financial assurance mechanisms in accordance with part 7035.2695. For unpermitted land disposal sites, the owner or operator shall submit a closure plan within 90 days after November 15, 1988. The agency shall approve the closure plan as part of the permit issuance procedure or as part of a submittal required by a closure document or other enforcement action. Compliance with the approved closure plan must be a condition of any permit, order, closure document, or stipulation agreement issued for the facility. The closure plan must be consistent with subparts 2, 4, and 5, part 7035.2635, and the applicable closure requirements of parts 7035.2665; 7035.2815, subpart 16; and 7035.2825 to 7035.2915.
A copy of the approved closure plan, and all revisions to the plan, must be kept at the facility until closure is completed and certified under part 7035.2635. Except for transfer facilities and other facilities that will not have waste present following closure, the agency will issue a closure document in accordance with part 7001.3055. The plan must identify steps needed to close each fill phase, if appropriate, and the entire site at the end of its operating life. The closure plan must include:
The owner or operator may amend the closure plan any time during the life of the facility. The owner or operator must amend the plan whenever changes in the operating plan or facility design affect the closure procedures needed and whenever the expected year of closure changes. If a permit modification as authorized in part 7001.3550 is needed, the owner or operator shall submit an amended closure plan with the modification request. In all other cases, the owner or operator must request a modification of the plan, or, for transfer facilities operated under an extended permit term, make a modification to the plan as provided under part 7001.3410, subparts 1, item D, and 2, within 60 days of any change or event that affects the closure plan.
The owner or operator shall notify the commissioner at least 90 days before final facility closure activities are to begin. If the permit for the facility has been terminated and a closure document has been issued, this requirement does not apply. However, the owner or operator must close the facility in accordance with procedures established in the closure plan and closure document.
Minn. R. agency 167, ch. 7035, SOLID WASTE MANAGEMENT FACILITY GENERAL TECHNICAL REQUIREMENTS, pt. 7035.2625
Statutory Authority: MS s 115.03; 115A.97; 116.07