Minn. R. agency 158, ch. 6131, PROCEDURES AND STANDARDS, pt. 6131.0210

Current through Register Vol. 49, No. 24, December 9, 2024
Part 6131.0210 - AMENDMENTS
Subpart 1.Application for amendment.

A proceeding for requesting an amendment of a permit to mine is commenced when the permittee files an application for an amendment with the commissioner. The application shall include information necessary for the commissioner to determine that the proposed amendment meets the lawful requirements and parts 6131.0010 to 6131.0340.

Subp. 2.Determination by commissioner.

Within 30 days after receipt of the application, the commissioner shall determine whether the proposed amendment constitutes a substantial change in the permit to mine.

If the commissioner determines that a substantial change would occur, the applicant shall follow the procedures for permit to mine applications in part 6131.0190.

If the commissioner determines that there would be no substantial change, the commissioner shall without a hearing allow the amendment with or without additional terms or conditions which are consistent with parts 6131.0010 to 6131.0340, or deny the applications stating reasons therefor.

Subp. 3.Demand for hearing.

If the commissioner processes the application without a hearing pursuant to subpart 2, the applicant may file with the commissioner a demand for hearing on the decision pursuant to part 6131.0190, subpart 4.

Minn. R. agency 158, ch. 6131, PROCEDURES AND STANDARDS, pt. 6131.0210

10 SR 277

Statutory Authority: MS s 93.461