Minn. R. agency 151, ch. 1300, pt. 1300.0130

Current through Register Vol. 49, No. 24, December 9, 2024
Part 1300.0130 - CONSTRUCTION DOCUMENTS
Subpart 1.Submittal documents.

Construction documents, special inspection and structural observation programs, and other data shall be submitted in one or more sets with each application for a permit.

Exception: The building official may waive the submission of construction documents and other data if the nature of the work applied for is such that reviewing of construction documents is not necessary to obtain compliance with the code.

The building officer may require plans or other data be prepared according to the rules of the Board of Architecture, Engineering, Land Surveying, Landscape Architecture, Geoscience and Interior Design, chapter 1800, and Minnesota Statutes, sections 326.02 to 326.15, and other state laws relating to plan and specification preparation by occupational licenses. If special conditions exist, the building official may require additional construction documents to be prepared by a licensed design professional.

Subp. 2.Information on construction documents.

Construction documents shall be dimensioned and drawn upon suitable material. Electronic media documents are permitted to be submitted when approved by the building official. Construction documents shall be of sufficient clarity to indicate the location, nature, and extent of the work proposed and show in detail that it will conform to the code and relevant laws, ordinances, rules, and regulations, as determined by the building official.

Subp. 3.Manufacturer's installation instructions.

When required by the building official, manufacturer's installation instructions for construction equipment and components regulated by the code, shall be available on the job site at the time of inspection.

Subp. 4.Site plan.

The construction documents submitted with the application for permit shall be accompanied by a site plan drawn to scale, showing the size and location of new construction and existing structures on the site, distances from lot lines, the established street grades, and the proposed finished grades, and it shall be drawn according to an accurate boundary line survey. In the case of demolition, the site plan shall show construction to be demolished and the location and size of existing structures and construction that are to remain on the site or plot. The building official may waive or modify the requirement for a site plan if the application for permit is for alteration or repair or when otherwise warranted.

Subp. 5.Examination of documents.

The building official shall examine or cause to be examined the accompanying construction documents to ascertain whether the construction indicated and described complies with the requirements of the code and other pertinent laws and ordinances.

Subp. 6.Approval of construction documents.

If the building official issues a permit, the construction documents shall be approved in writing or by a stamp, stating "Reviewed for Code Compliance," dated, and signed by the building official or an authorized representative. One set of the construction documents that were reviewed shall be retained by the building official. The other set shall be returned to the applicant, kept at the site of the work, and open to inspection by the building official or an authorized representative.

Subp. 7.Previous approvals.

The code in effect at the time of application shall be applicable.

Subp. 8.Phased approval.

The building official may issue a permit for the construction of foundations or any other part of a building or structure before the construction documents for the whole building or structure have been submitted, provided that adequate information and detailed statements have been filed complying with pertinent requirements of the code. The holder of the permit for the foundation or other parts of a building or structure shall proceed at the holder's own risk with the building operation and without assurance that a permit for the entire structure will be granted.

Subp. 9.Design professional in responsible charge.
A. The building official may require the owner to engage and designate on the building permit application a licensed design professional who shall act as the licensed design professional in responsible charge. If the circumstances require, the owner shall designate a substitute licensed design professional in responsible charge who shall perform the duties required of the original licensed design professional in responsible charge. The building official shall be notified in writing by the owner if the licensed design professional in responsible charge is changed or is unable to continue to perform the duties.

The licensed design professional in responsible charge shall be responsible for reviewing and coordinating submittal documents prepared by others, including phased and deferred submittal items, for compatibility with the design of the building.

When structural observation is required by the code, the inspection program shall name the individual or firms who are to perform structural observation and describe the stages of construction at which structural observation is to occur.

B. For the purposes of this part, deferred submittals are defined as those portions of the design that are not submitted at the time of the application and that are to be submitted to the building official within a specified period.

Deferral of any submittal items shall have the prior approval of the building official. The licensed design professional in responsible charge shall list the deferred submittals on the construction documents for review by the building official.

Submittal documents for deferred submittal items shall be submitted to the licensed design professional in responsible charge who shall review them and forward them to the building official with a notation indicating that the deferred submittal documents have been reviewed and that they have been found to be in general conformance with the design of the building. The deferred submittal items shall not be installed until their design and submittal documents have been approved by the building official.

C. Work regulated by the code shall be installed according to the reviewed construction documents, and any changes made during construction that are not in compliance with the approved construction documents shall be resubmitted for approval as an amended set of construction documents.

Minn. R. agency 151, ch. 1300, pt. 1300.0130

27 SR 1471; 32 SR 5; L 2007 c 140 art 4 s 61; art 13 s 4

Statutory Authority: MS s 16B.59; 16B.61; 16B.64; 326B.101; 326B.106; 326B.13