Minn. R. agency 141, ch. 4410, ENVIRONMENTAL ASSESSMENT WORKSHEET, pt. 4410.1600

Current through Register Vol. 49, No. 25, December 16, 2024
Part 4410.1600 - EAW COMMENT PERIOD

A 30-day period for review and comment on the EAW shall begin the day the EAW availability notice is published in the EQB Monitor.

Written comments shall be submitted to the RGU during the 30-day review period. The comments shall address the accuracy and completeness of the material contained in the EAW, potential impacts that may warrant further investigation before the project is commenced, and the need for an EIS on the proposed project.

The RGU may hold one or more public meetings to gather comments on the EAW if it determines that a meeting is necessary or useful. Reasonable public notice of the meetings shall be given prior to the meetings. All meetings shall be open to the public.

Minn. R. agency 141, ch. 4410, ENVIRONMENTAL ASSESSMENT WORKSHEET, pt. 4410.1600

Statutory Authority: MS s 116D.04