Within 45 days after acceptance of the application by the commission, the commission shall make a preliminary determination whether a permit may be issued or should be denied. If the preliminary determination is to issue a permit, the commission shall prepare a draft site permit for the project. The draft site permit must identify the person or persons who will be the permittee, describe the proposed LWECS, and include proposed permit conditions.
A draft site permit does not authorize a person to construct an LWECS. The commission may change the draft site permit in any respect before final issuance or may deny the site permit.
Minn. R. agency 138, ch. 7854, pt. 7854.0800
Statutory Authority: MS s 116C.695; 216F.05