Within 20 days of commission acceptance of an application for a pipeline routing permit under part 7852.2000, subpart 4, the commission shall provide published notice of acceptance of the application in a newspaper in each county in which a route is proposed by the applicant.
The notice must include:
A. identification of the applicant;B. the date of the commission's acceptance of the application;C. a brief description of the proposed facility including but not limited to size and type;D. a map showing the routes proposed in that county;E. the name and function of the public adviser and the address and telephone number where that person can be reached;F. locations where the pipeline routing permit application is available to the public;G. procedures for proposing alternate routes; andH. notice of public information meetings.Minn. R. agency 138, ch. 7852, PIPELINE ROUTE SELECTION PROCEDURES, pt. 7852.0900
13 SR 2046; L 2005 c 97 art 3 s 19Statutory Authority: MS s 116I.015; 216G.02