A person seeking a site permit or route permit for a large electric power generating facility must file three copies of the application for the permit with the PUC. Upon acceptance of the application, the commission will advise the applicant of how many copies of the application must be submitted to the PUC.
A person filing an application for a site permit or route permit shall provide the PUC with an electronic version of the application suitable for posting on the PUC's Web page.
Minn. R. agency 138, ch. 7850, pt. 7850.1700
Statutory Authority: MS s 116C.66; 216E.16