Current through Register Vol. 49, No. 27, December 30, 2024
Part 7835.3700 - AMOUNT OF CAPACITY PAYMENTS; CONSIDERATIONS The qualifying facility which negotiates a contract under part 7835.3600 must be entitled to the full avoided capacity costs of the utility. The amount of capacity payments must be determined through consideration of:
A. the capacity factor of the qualifying facility;B. the cost of the utility's avoidable capacity;C. the length of the contract term;D. reasonable scheduling of maintenance;E. the willingness and ability of the qualifying facility to provide firm power during system emergencies;F. the willingness and ability of the qualifying facility to allow the utility to dispatch its generated energy;G. the willingness and ability of the qualifying facility to provide firm capacity during system peaks;H. the sanctions for noncompliance with any contract term; andI. the smaller capacity increments and the shorter lead times available when capacity is added from qualifying facilities.Minn. R. agency 138, ch. 7835, RATES, pt. 7835.3700
Statutory Authority: MS s 216A.05; 216B.08; 216B.164