Schedule H must list the rates at which a nongenerating utility purchases energy and capacity. If the nongenerating utility has more than one wholesale supplier, schedule H must list the rates of that supplier from which purchases may first be avoided. If the nongenerating utility with more than one wholesale supplier also chooses to file schedules A and B, the data on schedules A and B must be obtained from that supplier from which purchases may first be avoided.
Minn. R. agency 138, ch. 7835, FILING REQUIREMENTS, pt. 7835.1100
Statutory Authority: MS s 216A.05; 216B.08; 216B.164