Rule 415. An amendment to an approved certificate of need for increased project costs will not be required if the total amount of excess does not exceed the sum of 15% of the approved project costs up to $1,000,000.00 and 10% of the approved project costs in excess of $1,000,000.00.
Mich. Admin. Code R. 325.9415