Section R. 299.2382 - Well completion operationsRule 2382.
(1) A permittee of a well shall use proper well control measures to avoid an uncontrolled flowing of the well. All fluids shall be produced or swabbed back to approved containers. A permittee of a well shall not use unlined earthen pits or reservoirs to contain fluids produced from the well during completion except as approved by the supervisor of mineral wells or authorized representative of the supervisor of mineral wells.(2) A permittee shall notify the supervisor of mineral wells or authorized representative of the supervisor of mineral wells at least 48 hours before the start of a well completion operation.Mich. Admin. Code R. 299.2382