Section 096-111-4 - Transition Schedule

The owner or operator of fixed-roof petroleum storage vessels located in Air Quality Control Regions III, IV and V shall have until July 1, 1991, to comply with the requirements under subsection (2)(A). In Air Quality Control Regions III, IV and V, the owner or operator of a fixed-roof petroleum storage vessel without a floating roof or other acceptable volatile organic compound emission control equipment shall adhere to the increments of progress contained in the following schedule and shall report to the department within 15 days of the prescribed deadline the status of compliance with each increment of progress.

A.Final plans for the floating roof, other necessary modifications or other acceptable volatile organic compound emission control equipment shall be submitted before November 1, 1989.
B. Contracts for installation of the floating roof, other modifications or other acceptable volatile organic compound emission control equipment or purchase orders for component parts shall be issued before March 1, 1990.
C. Initiation of on-site construction or installation of acceptable volatile organic compound emission control equipment shall begin before July 1, 1990.
D.Final compliance shall be achieved before July 1, 1991.