La. Admin. Code tit. 43 § XIII-3319

Current through Register Vol. 50, No. 9, September 20, 2024
Section XIII-3319 - What Must Be in the Baseline Assessment Plan [49 CFR 192.919]
A. An operator must include each of the following elements in its written baseline assessment plan: [ 49 CFR 192.919]
1. identification of the potential threats to each covered pipeline segment and the information supporting the threat identification (see §3317); [ 49 CFR 192.919(a)]
2. the methods selected to assess the integrity of the line pipe, including an explanation of why the assessment method was selected to address the identified threats to each covered segment. The integrity assessment method an operator uses must be based on the threats identified to the covered segment (see §3317). More than one method may be required to address all the threats to the covered pipeline segment; [ 49 CFR 192.919(b)]
3. a schedule for completing the integrity assessment of all covered segments, including, risk factors considered in establishing the assessment schedule; [ 49 CFR 192.919(c)]
4. if applicable, a direct assessment plan that meets the requirements of §3323, and depending on the threat to be addressed, of §§3325, 3327, or 3329; and [ 49 CFR 192.919(d)]
5. a procedure to ensure that the baseline assessment is being conducted in a manner that minimizes environmental and safety risks. [ 49 CFR 192.919(e)]

La. Admin. Code tit. 43, § XIII-3319

Promulgated by the Department of Natural Resources, Office of Conservation, Pipeline Division, LR 30:1277 (June 2004).
AUTHORITY NOTE: Promulgated in accordance with R.S. 30:501 et seq.