Kan. Admin. Regs. § 112-106-2

Current through Register Vol. 43, No. 46, November 14, 2024
Section 112-106-2 - Surveillance system plan
(a) Each applicant for a facility manager certification shall submit a surveillance system plan to the commission at least 120 days before the proposed opening of a racetrack gaming facility or lottery gaming facility.
(b) A facility manager shall not commence gaming activities until its surveillance system plan is approved by the commission.
(c) To be approved, the surveillance system plan shall include the following:
(1) A schematic showing the placement of all surveillance equipment;
(2) a detailed description of the surveillance system and its equipment;
(3) the policies and procedures for the surveillance department;
(4) the plans for staffing as required in K.A.R. 112-106-4;
(5) the monitoring activities for both the gaming area and adjacent areas;
(6) the monitoring activities for a detention room; and
(7) a list of the facility manager's personnel that may have access to the surveillance system.
(d) All proposed changes to the surveillance system plan shall be submitted by the director of surveillance to the commission for approval at least 30 days before the director of surveillance desires to implement the changes.

Kan. Admin. Regs. § 112-106-2

Authorized by and implementing K.S.A. 2009 Supp. 74-8772; effective Sept. 26, 2008; amended April 1, 2011.