Iowa Admin. Code r. 261-404.7

Current through Register Vol. 47, No. 11, December 11, 2024
Rule 261-404.7 - [Effective until 7/31/2024] Administration
(1)Notice of approval. The authority will notify successful applicants in writing of an approved request for funding. Notification will include the terms or conditions under which approval is granted.
(2)Agreement. After notifying the recipient of an award, the authority will issue an agreement. The agreement shall be between the recipient and the authority.
(3)Transmittal. The recipient must execute and return the agreement to the authority within 45 days of the transmittal of the final agreement from the authority. Failure to do so may be cause for the board to terminate the award.
(4)Disbursement of funds. Recipients shall submit requests for grant funds in the manner prescribed by the authority. Disbursements shall be made on a reimbursement basis. No advance disbursements shall be allowed. Disbursements may be withheld if applicable performance reports have not been received and approved. Individual requests for funds shall be made in an amount equal to or greater than $500 per request, except for the final draw of funds.
(5)Record keeping and retention. Recipients shall retain all financial records, supporting documents and all other records pertinent to the grant for five years after agreement closeout.
(6)Performance reports and reviews. Recipients shall submit performance reports to the authority as described in the policies and procedures handbook. The authority may perform annual project reviews and site inspections as necessary to ensure program compliance.
(7)Agreement amendments.
a. Any substantive change to a funded IEC project, including time extensions, budget revisions, and alterations to proposed activities, will be considered an agreement amendment. The recipient shall request an amendment in writing. No amendment shall be valid until approved by the board, except as provided in paragraph 404.7(7)"b " and confirmed in writing by the authority.
b. Staff approvals.
(1) Staff may approve one no-cost extension provided that the extension complies with subrule 404.4(5). Additional no-cost extensions shall be presented to the board for approval.
(2) Budget modifications. Any substantial modification of a project budget shall require board approval. Staff may approve budget modifications that are not substantial. For purposes of this subparagraph, "substantial modification" means a budget modification of either $10,000 or 10 percent of the total grant award, whichever is less.
(8)Agreement closeout. Upon agreement expiration or project completion, the authority shall initiate project closeout procedures.
(9)Compliance with state and local laws and rules. Recipients shall comply with these rules, with any provisions of the Iowa Code governing activities performed under this program, and with any applicable local rules.
(10)Noncompliance. At any time during a project, the IEC may, for cause, find that a recipient is not in compliance with the requirements of this program. At the board's discretion, remedies may include penalties up to and including the return of grant funds to the IEC. Findings of noncompliance may include the use of Iowa energy center funds for activities not described in the application; failure to complete approved activities in a timely manner; failure to comply with any applicable state or federal rules, regulations, or laws; or the lack of a continuing capacity of the recipient to carry out the approved project in a timely manner.

Iowa Admin. Code r. 261-404.7

Adopted by IAB January 30, 2019/Volume XLI, Number 16, effective 3/6/2019