Section 905 IAC 1-48-5 - Time allotted for review and action by the commission

Authority: IC 7.1-2-3-7; IC 7.1-7-3-3

Affected: IC 7.1-7

Sec. 5.

(a) The commission shall complete its review and take final action upon the application within sixty (60) days after receiving all information and documentation required by IC 7.1-7 and this rule, including, but not limited to, the following:
(1) The completed application form.
(2) The certification by the security firm that the manufacturing facility is in compliance with the requirements of IC 7.1-7-4-1(d)(3) and IC 7.1-7-4-6(b)(10) through IC 7.1-7-4-6(b)(15).
(3) A fully compliant service security agreement is executed with the final copy submitted to the commission.
(4) Product listing that complies with section 8 of this rule.
(5) Payment of the application fee.
(6) Floor plan.
(7) Any other outstanding matters required by the commission are satisfied.
(b) For an out-of-state or out-of-country manufacturing facility that the commission is unable to physically inspect, arrangements may be made for an independent provider approved by the commission to perform such inspection. The out-of-state approved inspection provider will be required to submit the results of the inspection directly to the commission via first class mail.

905 IAC 1-48-5

Alcohol and Tobacco Commission; 905 IAC 1-48-5; filed 12/29/2016, 3:49 p.m.: 20170125-IR-905160326FRA