Current through December 12, 2024
Section 675 IAC 12-6-3 - Design release; requirementAuthority: IC 22-13-2-13
Affected: IC 22-15-3
Sec. 3.
(a) No construction shall be done on a Class 1 structure until a design release has been issued by the division unless the construction is of a type specifically exempted from the design release requirements by section 4 of this rule. Design releases may be issued by the division.(b) If a foundation release is obtained under section 14 of this rule, construction may: (1) be done to the grade level only as provided for by section 14(c) of this rule; and(2) not go beyond that point without the issuance of a design release or a partial design release authorizing the further construction.(c) If a partial design release is obtained under section 15 of this rule, construction may be done to the extent of the partial design release but it may not exceed that scope without the issuance of a design release or another partial design release authorizing the further construction.Fire Prevention and Building Safety Commission; 675 IAC 12-6-3; filed Jul 17, 1987, 2:30 p.m.: 10 IR 2689, eff Aug 1, 1987 [IC 4-22-2-36 suspends the effectiveness of a rule document for 30 days after filing with the Secretary of State. LSA Document #87-53 was filed Jul 17, 1987.]; readopted filed Sep 11, 2001, 2:49 p.m.: 25 IR 530; filed Aug 30, 2006, 2:25 p.m.: 20060927-IR-675050108FRA; readopted filed Sep 21, 2007, 9:20 a.m.: 20071010-IR-675070388RFA; readopted filed Oct 10, 2007, 9:16 a.m: 20071031-IR-675070388RFA; readopted filed Aug 8, 2012, 8:08 a.m.: 20120905-IR-675120260RFAReadopted filed 7/3/2018, 2:22 p.m.: 20180801-IR-675180204RFAReadopted filed 6/10/2024, 8:09 a.m.: 20240710-IR-675230794RFA