Authority: IC 13-14-8-7; IC 13-15-2-1; IC 13-19-3-1
Affected: IC 13-30-2; IC 36-9-30
Sec. 4.
When the post-closure care requirements of this rule have been completed, the owner, operator, or permittee shall submit a certification statement signed by the owner, operator, or permittee and an independent registered professional engineer that the post-closure care requirements have been met and the MSWLF has stabilized. The post-closure certification will be deemed adequate, unless within ninety (90) days of receipt of the post-closure certification and subsequent review, the commissioner issues notice of the deficiency of post-closure, including actions necessary to correct the deficiency.
329 IAC 10-23-4