327 Ind. Admin. Code 8-3-2.1

Current through November 6, 2024
Section 327 IAC 8-3-2.1 - Permits for construction of small transient and small nontransient noncommunity public water systems

Authority: IC 13-14-8; IC 13-14-9; IC 13-15-1-2; IC 13-15-2-1; IC 13-18-3-1; IC 13-18-4-1

Affected: IC 13-11-2; IC 13-13-5-1; IC 13-18-2; IC 25-31-1-19

Sec. 2.1.

(a) Small transient and small nontransient noncommunity public water systems may construct facilities specified in 327 IAC 8-4-2 without obtaining a construction permit, provided that they have met all the conditions set forth in 327 IAC 8-4-2.
(b) For construction at small transient and small nontransient noncommunity public water systems that are not subject to subsection (c), the design as shown on an application, plans, and specifications may be certified by any of the following:
(1) A professional engineer.
(2) A licensed well driller.
(3) A licensed professional geologist.
(c) As required under IC 25-31-1-19 (a), design on construction and maintenance projects for:
(1) a county;
(2) a city;
(3) a town;
(4) a township;
(5) a school corporation; or
(6) any other political subdivision; must have a professional engineer certify that the design as shown on the application, plans, and specifications are in compliance with the rule.
(d) Where a permit is required, an application form shall be submitted in accordance with section 3 of this rule. If specifications for small transient and small nontransient noncommunity public water systems are not included in this section, the requirements of section 2 of this rule must be met.

327 IAC 8-3-2.1

Water Pollution Control Board; 327 IAC 8-3-2.1; filed Apr 24, 2006, 3:00 p.m.: 29 IR 2950; readopted filed Nov 21, 2007, 1:16 p.m.: 20071219-IR-327070553BFA; readopted filed Jul 29, 2013, 9:21 a.m.: 20130828-IR-327130176BFA
Readopted filed Jun 6, 2019, 1:59 p.m.: 20190710-IR-327190246BFA