Authority: IC 13-13-5-2; IC 13-14-8; IC 13-16; IC 13-18-4-1
Affected: IC 36-1-2-23
Sec. 5.
TYPE | PROCESSING FEE |
New wastewater treatment plant (except industrial): | |
Up to 500,000 gallons per day | $1,250 |
Greater than 500,000 gallons per day | $2,500 |
New industrial wastewater treatment plant (including pretreatment): | |
Up to 500,000 gallons per day for: | |
Biological or chemical treatment | $1,250 |
Physical treatment | $250 |
Greater than 500,000 gallons per day for: | |
Biological or chemical treatment | $2,500 |
Physical treatment | $500 |
WWTP expansion: | |
Up to fifty percent (50%) design capacity: | |
Greater than 500,000 gallons per day | $1,250 |
Up to 500,000 gallons per day | $625 |
Greater than fifty percent (50%) design capacity: | |
Greater than 500,000 gallons per day | $2,500 |
Up to 500,000 gallons per day | $1,250 |
327 IAC 3-5-5