Current through November 6, 2024
Section 170 IAC 5-3-2 - Federal regulations; revisionAuthority: IC 8-1-1-3; IC 8-1-22.5-4
Affected: IC 8-1-2; IC 8-1-22.5
Sec. 2.
(a) Indiana specific revisions to certain federal regulations incorporated in section 0.6 of this rule are as set forth in this section.(b)49 CFR 192.201(c) (Required capacity of pressure relieving and limiting stations) is revised to read as follows: (c)" Relief valves or automatic shutoff devices must be installed at or near each regulator station in a low-pressure distribution system, with a capacity to limit the maximum pressure in the main to a pressure that will not exceed the safe operating pressure for any connected and properly adjusted gas utilization equipment.".(c)49 CFR 192.201 is augmented to include an additional paragraph (a)(2)(iv) to read as follows: (a)" (2)(iv) At a minimum have a device installed that would notify the operator or the public of a malfunction.".(d)49 CFR 192.357 (Customer Meters and Regulators: Installation) is augmented to include an additional paragraph (e) to read as follows:(e)" An operator may not initiate or reinstate gas service without first ascertaining that: (1) the meter and regulator are: (A) properly sized and installed for their intended use;(B) pressure tight at the operating pressure; and(C) protected from reasonably anticipated outside forces, including, but not limited to, reasonably anticipated:(i) vehicular impact; and(ii) natural forces, including, but not limited to: (2) for residential customers, the piping from the meter to the customer's appliance valves is pressure tight at the operating pressure.".(e)49 CFR 192.365(b) (Service Lines; Location of Valves) is revised to read as follows: (b)" Each service line must have a shutoff valve in a readily accessible location that is outside of the building. The required shutoff valve may include, but is not limited to: (1) outside meter valves; or(f)49 CFR 192.373(a) (Service Lines: Cast Iron and Ductile Iron) is revised to read as follows: (a)" Cast or ductile iron pipe shall not be installed for service lines.".(g)49 CFR 192.375(a) (Installation of Plastic Pipe) is revised to read as follows: (a)" This provision takes effect after July 1, 2021. Each plastic service line outside a building must be installed below ground level, except that it may be installed in accordance with § 192.321(g). A flexible riser must be designed to withstand damage from outside or a casing must also be installed to protect the flexible riser from lawn mowers, weed eaters, hedge trimmers, and other possible sources of external damage.".(h)49 CFR 192.467 (External corrosion control: Electrical isolation) is augmented to include an additional paragraph (g) to read as follows: (g)" For the purposes of this section, "electrical isolation" and "electrically isolated" means a substantial resistance between a buried or submerged pipeline and an underground metallic structure. If the differential between pipe-to-soil of underground metallic structure is less than 100 millivolts, this may indicate an electrical isolation issue and further investigation shall be conducted to verify electrical isolation is adequate in accordance with paragraph (d) of this section.".(i)49 CFR 192.503 (Test Requirements - General). In addition to the language contained in 49 CFR 192.503 paragraphs (b), (c), and (d), paragraphs (a) and (e) are revised to read as follows: (a)" No person may operate a new segment of pipeline, or return to service a segment of pipeline that has been relocated, replaced, or has been abandoned previously, until: (1) it has been tested in accordance with this subpart and 49 CFR 192.619 to substantiate the maximum allowable operating pressure; and(2) each potentially hazardous leak has been located and eliminated.(e) No testing, by a medium other than natural gas under this subpart, may be done against a valve on a jurisdictional part of the system that is connected by the valve to a source of gas, unless a positive suitable means has been provided to prevent the leakage or admission of the testing medium into a jurisdictional part of the system. When performing a pressure test, the operator shall use a calibrated tool or chart.".(j)49 CFR 192.509(b) (Test Requirements for Pipelines to Operate at or below 100 psig) is revised to read as follows and 49 CFR 192.509 is augmented to include an additional paragraph (c) to read as follows: (b)" Each main that is to be operated at less than one (1) psig must be tested to at least ten (10) psig, and each main to be operated at or above one (1) psig must be tested to one hundred fifty percent (150%) of the maximum operating pressure or at least ninety (90) psig, whichever is greater.(c) Distribution pipelines tested to comply with this rule must be tested to meet at least the durations specified in the Gas Piping Technology Committee guidelines under section 192.509 and 192.513, for the applicable pipeline material, size, and lengths, except no duration shall be required to exceed 24 hours.".(k)49 CFR 192.511 (Test Requirements for Service Lines). In addition to the language contained in 49 CFR 192.511 paragraph (a), paragraphs (b) and (c) are revised to read as follows: (b)" Each segment of a service line (other than plastic) stressed under twenty percent (20%) SMYS must be tested at one hundred fifty percent (150%) of the maximum operating pressure or at least to ninety (90) psig, whichever is greater. The test procedure used must ensure discovery of all potentially hazardous leaks in the segment being tested.(c) Each segment of a service line (other than plastic) stressed to twenty percent (20%) or more of SMYS must be tested in accordance with Section 192.505 or 192.507, whichever is applicable, of this subpart.".(l)49 CFR 192.553(c) (Subpart K - Uprating; General Requirements) is revised to read as follows: (c)" Written plan. Each operator who uprates a segment of pipeline shall establish a written procedure that will ensure that each applicable requirement of this subpart is complied with. An operator shall submit a copy of its written uprate plan to the division at least thirty (30) days before work commences under the plan, and submit to the division all subsequent revisions of the plan prior to performing work under those provisions. The operator shall submit to the Division a cover letter summarizing the revisions.".(m)49 CFR 192.553 (Subpart K - Uprating; General Requirements) is augmented to include an additional paragraph (e) to read as follows: (e)" Service regulators supplying gas from transmission lines or distribution mains that are being uprated under this subpart shall meet the requirements of Section 192.197.".(n)49 CFR 192.557(b)(5) and (c) (Uprating: Steel Pipelines to a Pressure That Will Produce a Hoop Stress less than 30 Percent of SMYS; Plastic, Cast Iron and Ductile Iron Pipelines) are revised to read as follows: (b)" (5) Isolate by physical separation all mains between the segment of pipeline in which the pressure is to be increased from an adjacent segment that will continue to be operated at the lower pressure, except the mains that are required to supply through a pressure regulator (with approved overpressure protection designed in accordance with Section 192.195), the adjacent segment that will continue to be operated at the lower pressure; and(c) After complying with paragraph (b) of this section, the increase in maximum allowable operating pressure must be made in increments that are equal to 10 p.s.i. (69 kPa) gage or 25 percent of the total pressure increase, whichever produces the fewer number of increments. The highest pressure at which the pipeline is surveyed is the newly established MAOP. Whenever the requirements of paragraph (b)(6) of this section apply, there must be at least two approximately equal incremental increases.".(o)49 CFR 192.605 (Procedural manual for operations, maintenance, and emergencies) is augmented to include an additional paragraph (f) to read as follows: (f)" The written manual required by paragraph (a) of this section, referred to as the plan in this subsection, shall ensure the safe operation of the operator's pipeline facilities. The plan shall include, by sections, the emergency, operations, and maintenance procedures for all the pipeline facilities and shall include procedures for handling abnormal operations. This plan, when submitted, becomes a regulation for the particular operator who filed it. In addition, an operator shall: (1) submit a copy of the plan to the division;(2) keep records necessary to administer the plan effectively;(3) revise the plan as: (A) experience dictates; and(B) exposure of the facilities and changes in operating conditions might warrant; and(4) submit to the division all subsequent revisions of the plan not later than twenty (20) days after the effective date of the changes. Minor revisions may be made in a cover letter.".(p)49 CFR 192.615 (Emergency Plans) is augmented to include an additional paragraph (d) to read as follows: (d)" Each operator shall publish a listing in the current telephone directory of each community that it serves or in a conspicuous location on its publicly available website whereby a responsible employee or agent of the operator may be reached on a twenty-four (24) hour basis.".(q)49 CFR 192.616 (Public Awareness) is augmented to include an additional paragraph (i) to read as follows: (i)" The operator's public awareness program shall include, at a minimum, a plan to directly contact appropriate government organizations and emergency responders at least once every four years for organizations that have not affirmatively attended group public awareness meetings at least once every four years.".(r)49 CFR 192.723 (Distribution Systems: Leakage Surveys and Procedures) is revised to read as follows: (a)" Each operator of a distribution system shall conduct periodic leakage surveys in accordance with this section.(b) A leak survey using gas detection equipment shall be conducted in: (2) areas of high occupancy buildings as identified in the operator's operations and maintenance procedures, including, but not limited to: (E) commercial buildings, including commercial box-style warehouse stores;(I) assisted living centers; and(J) identified sites in the operator's plan;(3) built-up residential areas where continuous pavement exists; and(4) other areas as the commission may direct; once each calendar year at intervals not exceeding fifteen (15) months. The surveys in business districts and areas of high occupancy buildings, listed in subdivisions (1) and (2), shall be made at least to the meter outlet. Tests shall include tests of the atmosphere in utility manholes, at cracks in the pavement and sidewalks and other locations providing an opportunity for finding gas leakage.(c) Leakage surveys of the distribution system outside of the areas as listed in paragraph (b) must be made as frequently as necessary but at least once every five (5) years at intervals not to exceed sixty-three (63) months. A vegetation type survey shall not be used as a single means of leakage control.(d) Each operator shall establish and execute a plan by which it will periodically survey each customer-owned service line for leakage once every five (5) calendar years at intervals not to exceed sixty-three (63) months. For purposes of this section, the term "customer-owned service" shall mean buried metallic gas carrying piping that is between the outlet of the meter and the entry of the building wall of a residential dwelling. The term does not include the following: (2) Services directly off mains that have an operating pressure of greater than sixty (60) psig.(3) Diversions to structures other than the residential dwelling located on the premises.(4) Services with meter settings adjacent to the structure being served.(e) All leaks reported, regardless of the origin of the reports, shall be recorded on suitable report forms. These report forms must provide space for all pertinent information. Each leak reported shall be accounted for, and actions taken in response to leaks shall be documented and filed in a systematic manner. (1) All leaks reported shall be investigated promptly and classified in accordance with procedures outlined in the operator's operations and maintenance plan. The procedures shall include acceptable response times and shall ensure that gas leakage that is hazardous to life or property shall receive immediate attention for repairs.(2) Leak indications where repairs are not completed shall be rechecked on subsequent surveys, depending on the operator's classification and in accordance with the operator's procedures.(f) An operator shall document surveys, inspections, and repairs made. These records, along with all other routine or unusual inspections and repairs, shall be kept in the file of the operating company.".(s)49 CFR 192.740(a) (Pressure regulating, limiting, and overpressure protection - Individual service lines directly connected to production, gathering, or transmission pipelines) is revised to read as follows: (a)" This section applies, except as provided in paragraph (c) of this section, to any service line directly connected to a production, gathering, or transmission pipeline that serves three (3) or more customers.".(t)49 CFR 192.805(h) (Qualification Program) is revised to read as follows: (h)" Provide training to individuals performing covered tasks to ensure that the individuals have the knowledge and skills needed to perform the tasks, which is the operator qualification training. An operator shall have and follow a written training program for employees performing covered tasks. When assigning training to an employee, an operator may modify the type of training considering the employee's prior experience with the operator's gas system, tools, and equipment; nonetheless the training shall include, at a minimum: (2) re-qualification training; and(3) training on tools and equipment that will be utilized by the employee, with the following considerations: (A) Training may be accomplished by the tool or equipment vendor or manufacturer's representative, or by an operator's designated trainer, supervisor, or a competent employee or designee.(B) Additional training is only required on uniquely operating tools and equipment, where the equipment's functionality varies by operation and not only by manufacturing brand. The training shall provide the individuals performing covered tasks have the necessary knowledge and skills to perform these tasks in a manner that ensures the safe operation of pipeline facilities; and".
(u)49 CFR 192.1003 (What do the regulations in this subpart cover?) is revised to read as follows: (a)" General. Unless exempted in paragraph (b) of this section this subpart prescribes minimum requirements for an IM program for any gas distribution pipeline covered under this part, including liquefied petroleum gas systems. A gas distribution operator, other than a master meter operator or a small LPG operator, must follow the requirements in §§ 192.1005 through 192.1013 of this subpart. A master meter operator or small LPG operator of a gas distribution pipeline must follow the requirements in § 192.1015 of this subpart.".(v)49 CFR 195.402 (Procedural manual for operations, maintenance, and emergencies) is augmented to include an additional paragraph (g) to read as follows: (g)" The written manual required by paragraph (a) of this section, referred to as the plan in this subsection, shall ensure the safe operation of the operator's pipeline facilities. The plan shall include, by sections, the emergency, operations, and maintenance procedures for all the pipeline facilities and shall include procedures for handling abnormal operations. This plan, when filed, becomes a regulation for the particular operator who filed it. In addition, an operator shall: (1) submit a copy of the plan to the division;(2) keep records necessary to administer the plan effectively;(3) revise the plan as: (A) experience dictates; and(B) exposure of the facilities and changes in operating conditions might warrant; and(4) submit to the division all subsequent revisions of the plan not later than twenty (20) days after the effective date of the changes. Minor revisions may be made in a cover letter.".(w)49 CFR 195.440 (Public Awareness) is augmented to include an additional paragraph (i) to read as follows: (i)" The operator's public awareness program shall include, at a minimum, a plan to directly contact appropriate government organizations and emergency responders at least once every four years for organizations that have not affirmatively attended group public awareness meetings at least once every four years.".(x)49 CFR 195.505(h) (Qualification Program) is revised to read as follows: (h)" Provide training to individuals performing covered tasks to ensure that the individuals have the knowledge and skills needed to perform the tasks, which is the operator qualification training. An operator shall have and follow a written training program for employees performing covered tasks. When assigning training to an employee, an operator may modify the training considering the employee's prior experience with the operator's gas system, tools, and equipment; nonetheless the training shall include, at a minimum: (2) re-qualification training; and(3) training on tools and equipment that will be utilized by the employee, with the following considerations: (A) Training may be accomplished by the tool or equipment vendor or manufacturer's representative, or by an operator's designated trainer, supervisor, or a competent employee or designee.(B) Additional training is only required on uniquely operating tools and equipment, where the equipment's functionality varies by operation and not only by manufacturing brand. The training shall provide the individuals performing covered tasks have the necessary knowledge and skills to perform these tasks in a manner that ensures the safe operation of pipeline facilities; and".
(y)49 CFR 195.575 (Which facilities must I electrically isolate?) is augmented to include an additional paragraph (f) to read as follows: (f)" For the purposes of this section, "electrical isolation" and "electrically isolated" means a substantial resistance between a buried or submerged pipeline and an underground metallic structure. If the differential between pipe-to-soil of underground metallic structure is less than 100 millivolts, this may indicate an electrical isolation issue and further investigation shall be conducted to verify electrical isolation is adequate in accordance with paragraph (d) of this section.".Indiana Utility Regulatory Commission; No. 32885: Minimum Safety Standards for Transportation of Gas and Related Pipeline Facilities Rule 2; filed May 12, 1972, 10:30 a.m.: Rules and Regs. 1973, p. 537; filed May 7, 1982, 2:00 p.m.: 5 IR 1176; readopted filed Jul 11, 2001, 4:30 p.m.: 24 IR 4233; readopted filed Apr 24, 2007, 8:21 a.m.: 20070509-IR-170070147RFA; filed Feb 9, 2010, 9:24 a.m.: 20100310-IR-170090190FRAFiled 5/27/2016, 11:39 a.m.: 20160622-IR-170150424FRAFiled 3/17/2022, 12:34 p.m.: 20220413-IR-170210213FRAFiled 5/24/2023, 3:24 p.m.: 20230621-IR-170220324FRA